Work Progress 15-02-2016
1 OVERALL VIEW FROM JALAN PJU 1A-3
2 OVERALL VIEW_2
3 BLOCK 1_LEVEL 7_ CABINETRY INSTALLATION IN PROGRESS
4 BLOCK 1_LEVEL 23_ CORRIDOR CLEANING WORK COMPLETED
5 BLOCK 2_LEVEL 13_ CABINETRY INSTALLATION IN PROGRESS
6 BLOCK 2_LEVEL 23_ CORRIDOR CLEANING WORK COMPLETED
7 BLOCK 3_LEVEL 19_ CABINETRY  INSTALLATION IN PROGRESS
8 BLOCK 4_LEVEL 5_ CABINETRY INSTALLATION COMPLETED
9 BLOCK 4_LEVEL 6_ CABINETRY INSTALLATION IN PROGRESS
10 PODUIM_CLUB HOUSE_ALUMINUM GLASS PANEL INSTALLATION IN PROGRESS
11 PODUIM_CLUB HOUSE_SWIMMING POOL PEBBLE WASH IN PROGRESS
block 3-Cleaning & light fitting is completed
block 4-cleaning and light fitting is completed
BLOCK 5-cleaning and painting is in progress