Work Progress 29-01-2015
OVERALL VIEW FROM SALES GALLERY
OVERALL VIEW FROM JALAN PJU 1A-3
BLOCK 1 ROOF SLAB STRUCTURE IN PROGRESS. BLOCK 2 ROOF SLAB STRUCTURE COMPLETED
BLOCK 1_LEVEL 3 TO 9_UNIT FLOOR TILING COMPLETED
BLOCK 1_LEVEL 3 TO 12_EXTERNAL SEALER PAINTING IN PROGRESS
BLOCK 2_LEVEL 3 TO 12_EXTERNAL PLASTERING IN PROGRESS
BLOCK 2_LEVEL 10 TO 12 INTERNAL PLASTER CEILING COMPLETED
BLOCK 3_LEVEL 5 TO 12_ INTERNAL FLOOR SCREEDING WORKS COMPLETED
BLOCK 3_LEVEL 14 to 16_INTERNAL M&E WORKS IN PROGRESS
BLOCK 4_LEVEL1 TO 12_EXTERNAL PLASTERING IN PROGRESS
BLOCK 5_LEVEL 6 TO 9_INTERNAL PLASTER CEILING COMPLETED
BLOCK 5_LEVEL 9 TO 10_UNIT TILING IN PROGRESS
BLOCK 5_LEVEL 16 TO 18_BRICKWORKS IN PROGRESS
BLOCK 5_LEVEL 24_SLAB FORMWORK IN PROGRESS
FACILITIES PODIUM_SWIMMING POOL CASTED