Work Progress 03-12-2014
OVERALL VIEW
OVERALL VIEW FROM SALES GALLERY
OVERALL VIEW FROM JALAN PJU 1A-3
BLOCK 1 & 2_LVL 22_RC STRUCTURE IN PROGRESS
BLOCK 1_LVL 3 TO 8_ INTERNAL PLASTER CEILING COMPLETED
BLOCK 1_LVL 3 TO 12_EXTERNAL PLASTERING IN PROGRESS
BLOCK 2_LVL 3 TO 7_PLASTER CEILING WORKS COMPLETED
BLOCK 2_LVL 3 TO 9_CONDUITS & WIRING COMPLETED_1
BLOCK 3_LVL15 TO 17_CORRIDOR BRICKWORK IN PROGRESS
BLOCK 3_LVL 9 to 11_ INTERNAL M&E WORKS IN PROGRESS_1
BLOCK 4_LVL 3 TO 6_INTERNAL PLASTER CEILING IN PROGRESS
BLOCK 5_LVL10 & 11_INTERNAL WALL PLASTERING IN PROGRESS
BLOCK 5_LVL 4 TO 7_ INTERNAL FLOOR TILING IN PROGRESS
BLOCK 5_LVL 11_INTERNAL BRICKWORKS COMPLETED
BLOCK 5_LVL 21 STRUCTURE IN PROGRESS
FACILITIES PODIUM IN PROGRESS