Work Progress 09-04-2015
OVERALL VIEW FROM SALES GALLERY
OVERALL VIEW FROM JALAN PJU 1A-3
OVERALL VIEW_2
BLOCK 1 & 2_RC STRUCTURE SLAB COMPLETED
BLOCK 1_EXTERNAL PLASTERING IN PROGRESS (LEVEL 13 TO ROOF)
BLOCK 1_LEVEL 3 TO 12_ WINDOW OUTER FRAME INSTALLATION IN PROGRESS
BLOCK 1_LEVEL 15_ INTERNAL FLOOR SCREEDING WORKS COMPLETED
BLOCK 2_LEVEL 3 TO 12_ WINDOW OUTER FRAME INSTALLATION IN PROGRESS
BLOCK 2_LEVEL 16 INTERNAL PLASTER CEILING COMPLETED
BLOCK 2_LEVEL 17_INTERNAL M&E WORKS COMPLETED
BLOCK 3_LEVEL 16_INTERNAL M&E WORKS COMPLETED
BLOCK 3_WATER TANK LEVEL_R.C. STRUCTURE IN PROGRESS
BLOCK 4_LEVEL 3 TO 12_EXTERNAL PLASTERING IN PROGRESS
BLOCK 4_LEVEL 4 TO 9_SCREEDING WORKS COMPLETED
BLOCK 4_LEVEL 7 TO 9_INTERNAL PLASTER CEILING COMPLETED
BLOCK 5_LEVEL 12_ TILING WORK IN PROGRESS
BLOCK 5_LEVEL 13 TO 15_ CEILING WORK IN PROGRESS
BLOCK 5_LEVEL 14 & 15_ M&E  WORKS COMPLETED
BLOCK 5_LIFT MOTOR ROOM_STRUCTURE IN PROGRESS
PODUIM_CLUB HOUSE RC STRUCTURE IN PROGRESS